Tuesday, July 13, 2010
Two Story
On June 25th we set a 3000 sq.ft. two story in Brattleboro, VT. This home was set on an existing foundation which the customer had to remove the roof before we could set the home. This project took us just under 2 weeks to complete. The finish work that needed to be done was drywall on marriage lines, floor transitions, siding on the gable ends, roof shingles for the top 5' of roof and soffit/fascia installation. The plumbing connections between units and electrical was completed by the homeowners contractors. This is, so far, the quickest timeframe for finishing a home and High Performance Modular would like to say thank you to the contractors who made it possible.